The operational sequence is a continuous work on two tanks in parallel, and with an overlap of approximately 3 days. An ideal overlap for the two working teams which can then concentrate their resources in a best possible way to achieve highest possible efficiency.
The tanks will be insulated with PASSER Marine’s spray foam solution and will have our Patented Tough Coat® product on strategic places for increased protection and longer lifetime.
The series of 8 tanks has a 1.000cbm gross volume each. All tanks will be installed with a variable insulation thickness around the periphery to accommodate the low boil-off rate of 0.25 %/24h.